TA Decision Model

Interactive Turnaround Schedule Visualization and Risk Assessment

Key Performance Indicators

Contractor Peak

N/A

Max Overlap

0

Capacity Check

N/A

Avg Yearly Risk

Timeline

Jan 25
Feb 25
Mar 25
Apr 25
May 25
Jun 25
Jul 25
Aug 25
Sep 25
Oct 25
Nov 25
Dec 25
Unit A
25-04-01 - 25-05-05
Unit B
25-05-01 - 25-06-04
Unit C
25-06-20 - 25-07-24
Unit D
25-07-20 - 25-08-23
Unit F
27-01-01 - 27-02-04
Unit G
27-01-06 - 27-02-09
Unit H
26-01-16 - 26-02-24
Unit I
26-03-27 - 26-04-25
Unit J
26-06-05 - 26-07-19
Unit K
26-08-14 - 26-09-20
Unit L
26-10-23 - 26-11-23
Unit M
27-01-01 - 27-02-04
Unit N
27-03-12 - 27-04-20
Unit O
27-05-21 - 27-06-19
Unit P
27-07-30 - 27-09-12
Unit Q
27-10-08 - 27-11-14